• Md Munna Ali

    Sunday, 12 September 2021

    একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়। তার সম্ভাব্য নমুনা।

     





    একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়। তার সম্ভাব্য নমুনা।


    1. Structure = 35%
    2. Brick work = 6%
    3. Wood work = 5%
    4. Metal work = 2%
    5. Plambing and Sanitary = 6%
    6. Electrical work = 7%
    7. Plaster work = 4%
    8. General Floor Tiles work = 6%
    9. Toilet & Kit wall Tiles work = 3%
    10. Aluminium work = 4%
    11. EME (Lift, Generator, Substation) = 10%
    12. Paint work = 3%
    13. Others civil work = 6%
    14. Utility connection & Bill = 3%
    Total = 100%

    STRUCTURE 35%
    - Footing & Column Padestal = 20%
    - Grade Beam, UGWR top Slab = 5%
    - GF Column, Stair etc = 4%
    - 1st Floor Slab = 9%
    - Typical Floor Column (5x3%) = 15%
    - 2nd floor slab to roof slab (5x8) = 40%
    - Roof top = 7%
    TOTAL = 100% (৩৫% যেভাবে আসবে।)

    BRICK WORK 6%
    - GF Brick work = 6%
    - 1st floor Brick work = 18%
    - 2nd floor Brick work = 18%
    - 3rd floor Brick work = 18%
    - 4th floor Brick work = 18%
    - 5th floor Brick work = 18%
    -Roof Top Brick work = 4%
    TOTAL = 100% (৬% যেভাবে হবে।)

    WOOD WORK 5%
    - Door frame = 40%
    - Main Door Shutter = 15%
    - Partex Door Shutter = 35%
    - Cat Door & Accessories = 10%
    TOTAL = 100% (৫% যেভাবে হবে।)

    METAL WORK 2%
    - Window grill = 55%
    - Verandah Railling = 20%
    - Stair Railling = 10%
    - Main gate, Gen-Sub, safety grill = 15%
    TOTAL = 100% (২% যেভাবে হবে।)

    PLAMBING & SANITARY 6%
    - uPVC vertical line thru duct = 25%
    - GI line work = 30%
    - Fixture & Fittings = 40%
    - Ground Floor = 5%
    TOTAL = 100% (৬% যেভাবে হবে।)

    ELECTRICAL - 7%
    - Conduiting inside slab = 10%
    - Conduiting on wall i/c MK box=15%
    - Cabling work = 55%
    - Switch-Socket = 20%
    TOTAL = 100% (৭% যেভাবে হবে।)

    PLASTER 4%
    - Ceiling plaster = 20%
    - Internal wall plaster = 50%
    - Outside plaster/facing bricks = 30%
    TOTAL = 100% (৪% যেভাবে হবে।)

    GENERAL FLOOR TILES 6%
    - General floor & Verandah = 75%
    - Stair, typical lobby & lift wall = 20%
    - GF lift lobby, wall, reception = 5%
    TOTAL = 100% (৬% যেভাবে হবে।)

    TOILET & KIT WALL TILES = 3%
    - Bath wall = 60%
    - Kitchen wall = 20%
    - Bath floor = 9%
    - Bath counter top = 4%
    - Kitchen floor = 3%
    - Kitchen counter top =4%
    TOTAL = 100% (৩% যেভাবে হবে।)

    ALUMINIUM WORK 4%
    - Outer framing-window sliding= 40%
    - Glass shutter-window sliding = 30%
    - Verandah sliding = 20%
    - Toilet high window = 5%
    - Comnon area = 5%
    TOTAL = 100% (৪% যেভাবে হবে।)

    EME 10%
    - Lift = 50%
    - Generator = 25%
    - Substation = 20%
    - PABX, Fire extinguisher etc = 5%
    TOTAL = 100% (১০% যেভাবে হবে।)

    PAINT WORK = 3%
    - Upto putty = 40%
    - Internal wall&ceiling 1st coat= 20%
    - Internal wall&ceiling 2nd coat= 15%
    - Outside paint/ceramic Tites = 25%
    TOTAL = 100% (৩% যেভাবে হবে।)

    OTHERS CIVIL WORK = 6%
    - Boundary wall = 30%
    - Line terracing/Roof top paver= 15%
    - LOGO, Gardening & others = 4%
    - GF BBC = 14%
    - GF pavement & footpath dev = 10%
    - Lintel, F/slab, drop wall, counter slab = 20%
    - Cable tray = 1%
    - Sanitary duct cover, ceiling etc= 4%
    - Reception desk, letter box = 2%
    TOTAL = 100% (৬% যেভাবে হবে।)

    UTILITY CONNECTION & BILL = 3%
    - DESA/DESCO = 35%
    - TITAS = 20
    - WASA = 15%
    - Utility bills = 30%
    TOTAL = 100%